PowerScale - WMR
Primary storage · VK6 · Westmere · KOVAAct nowRecommendation. Reaches 85% around 17 Jan 2027 - order capacity now (about 1.10 PiB to cover 12 months)
The storage estate holds 10.97 PiB usable, 63.6% used (3.99 PiB free). Each system is forecast to the 85% procurement trigger, the point to have more capacity ordered by. Not current: Data Domain - WMR (no data), Data Domain - HLD (no data), Data Domain - PEV (no data).
Risk-ranked. Each chart shows the last 90 days of fill, the projection at the current trend (dashed) and where it crosses the 85% trigger (red dot).
Recommendation. Reaches 85% around 17 Jan 2027 - order capacity now (about 1.10 PiB to cover 12 months)
Recommendation. Reaches 85% around 24 Feb 2027 - order capacity now (about 873.5 TiB to cover 12 months)
Recommendation. Reaches 85% around 16 Mar 2027 - approve and order within 3 months (about 108.6 TiB to cover 12 months)
Recommendation. Reaches 85% around 21 Mar 2027 - approve and order within 3 months (about 105.9 TiB to cover 12 months)
Recommendation. Reaches 85% around 22 Mar 2027 - approve and order within 3 months (about 196.5 TiB to cover 12 months)
Recommendation. Reaches 85% around 5 Apr 2027 - approve and order within 3 months (about 601.3 TiB to cover 12 months)
Recommendation. Reaches 85% around 6 Apr 2027 - approve and order within 3 months (about 270.9 TiB to cover 12 months)
Recommendation. Reaches 85% around 12 Apr 2027 - approve and order within 3 months (about 264.0 TiB to cover 12 months)
Recommendation. Reaches 85% around 12 Apr 2027 - approve and order within 3 months (about 235.0 TiB to cover 12 months)
Recommendation. Reaches 85% around 17 June 2027 - include in the next 12 months' budget (about 547.8 TiB to cover 12 months)
Recommendation. Reaches 85% around 17 June 2027 - include in the next 12 months' budget (about 547.8 TiB to cover 12 months)
Not reporting: Data Domain - WMR, Data Domain - HLD, Data Domain - PEV — no capacity data is being received, so these systems are not forecast or included in the totals. Restore monitoring access to include them.
Capacity is each system's physical usable capacity (after RAID), not logical or effective data. Data Domain excludes Cloud Tier (a licence quota, not local disk).
Trend is a least-squares fit over the last 90 days of daily samples. Where a system had a one-off step change (a migration or large clean-up) the trend is measured from that step. Backup appliances clean up weekly, so their trend is measured across the clean-up cycle. Last 30 days is the actual change, not the fitted one.
Reaches 85% projects the trend to the procurement trigger; anything beyond three years is not a planning number. Add for 12 months is the usable capacity to add to stay under 85% for a year at the current trend.
Status: Act now = over 90%, reaching 85% within 3 months, or licensed capacity exceeded; Watch = over 80% or within 6 months; Budget = within 12 months. Confidence is High with 20+ days of a consistent trend, Medium with less, and Low for stale or short histories. A system whose newest data is more than 3 days older than the rest is marked with its data age.
Summarised in the Executive Board Report; per-volume detail is on the Capacity page.